2022-05-11(237)Engineering law and the ICE Contracts

6. RECOVERY BY CONTRACTOR OF COSTS DUE TO INSTRUCTIONS OR DIRECTIONS. To try to define the practical scope of this, possibly the most important provision in these Conditions, it is necessary to consider separately the four ingredients specified for a claim by the contractor: (a) “instructions or directions”, and (b) “in pursuance of Clause 5 or sub-clause (1) of this Clause”, and (c)“which involve the Contractor in delay or disrupt his arrangements or methods of construction", (d) “so as to cause him to incur cost beyond that reasonably to have been foreseen by an experienced contractor at the time of tender”. None of these requirements is free from difficulty.

(a) To give the contractor a right to compensation the instruction or direction need not be in writing, or confirmed by the contractor in writing. Notice of any claim to extra payment is required under cl. 52 (4) but only “as soon as reasonably possible after the happening of the events giving rise to the claim”, which is the incurring of extra cost by the contractor, not the receipt of the instruction. Thus the engineer may receive notice of a claim for extra money founded on some misunderstanding or misinterpretation of an instruction or much larger than he expected, when it is too late for him to clarify or alter the instruction involved.

No distinction is intended between an instruction or direction and an order (“instructions including the ordering”—cl. 26 (2) (b) and see cl. 40 (1) and N. 11).

Possibly a requirement of the engineer authorised by the Conditions (e.g. cls. 14 (2), 16, 19 and 31, and see cls. 49 and 50) is distinct from an instruction or direction, and does not bring this sub-clause into effect (but see the description of what is “required” by the?Engineer under cls. 49 (2) and 50 as “work ordered” in cl. 60 (5) (c)). For cl. 20 (2) refer to p. 100, N. 6.

The engineer may avoid a claim under this clause by avoiding instructions and directions. For example, if the specification says that the contractor may not use explosives without the engineer’s consent, then the engineer may prohibit explosives where necessary without having to instruct the contractor not to use them. The engineer also has a general wide power of refusing approval under sub-clause (2) of this clause. He will also have to avoid later “instructing” the contractor to stop work for which he has refused consent or approval, and instead merely point out that the method of working has not been approved.

It does not appear that in such a case the contractor is entitled to argue that the refusal of approval amounts to an instruction, or claim merely on the grounds that the engineer’s refusal of consent or approval was unreasonable, although he will have a claim if the engineer is not acting on correct principles in good faith (p. 416). The argument that cls. 51 and 52 may entitle the contractor to extra payment where refusal of approval leads to changes in temporary works is discussed on p. 170. N. 4. Whether positive action by the engineer following disapproval, under cls. 39 or 40, entitles the contractor to claim under this clause is discussed in the next part of this note. The engineer as a last resort may give?a certificate for forfeiture under cl. 63 where his disapproval is being flouted. By persisting with doubtful temporary works or methods the contractor also takes the risk of liability for failure or damage to the temporary or permanent works or for injury or damage to the person or property of third parties (p. 52, N. 2).

It is a strange result that the engineer is in a position very much to restrict the scope of this clause in so far as he can direct the works by stating in the specification what the contractor is not to do without his consent, or even rely on cl. 13 (2), rather than positively instructing the contractor during the contract.

(b) If an instruction or direction from the engineer is provided for specifically in another clause of the Conditions, the instruction or direction normally would be said to be issued in pursuance of that clause, and not in pursuance of sub-cl. (1). This interpretation is strengthened by the specific statement in cl. 5 that an instruction under that clause is to be regarded as an instruction issued in accordance with cl. 13 and the separate reference here to an instruction in pursuance of cl. 5, both unnecessary if every instruction or direction by the engineer within the contract is to be deemed to be given “in pursuance of…sub-clause (1) of this Clause”. Again, in contrast to, e.g., cls., 26 (2) (b) and 48 (1), cl. 71 (2) (a) says that the engineer may “instruct the Contractor pursuant to Clause 13”.

The reference to variations (N. 11) and the words in brackets in cl. 12 (3), perhaps pointing the other way, increase the confusion.

If there is this distinction that the right to extra payment under this clause does not apply to instructions given under the terms of some other clause of the Conditions, the reason for it, if there is a reason, is presumably that the contractor can allow in his tender for the possibility of delay or disruption due to exercise of the engineer’s power to give instructions mentioned in other clauses of the contract, but not under the wide and general power in this clause. Unfortunately, the practical results of the distinction are distinctly odd. The contractor has a specific right to payment for disruption due to an instruction under cl. 5, but not to disruption due to an order under cls. 38 or 39 to remove or uncover work previously approved, or under cl. 36 if a test instructed causes delay or disruption. The contractor may have a claim due to exercise of any of the engineer’s powers arising only out of this cl. 13 (1), but what of instructions empowered by the specification ?

On the other hand, if the wider interpretation is intended, that the contractor has a remedy under this sub-clause for delay or disruption due to any instructions or directions whether mentioned elsewhere or not, it would have been easy to say so by leaving out “in pursuance” to and including the second “Clause” in the opening line of this sub-clause.

Unfortunately the arguments are so evenly balanced that it would be rash to give an opinion as to the solution of this conundrum, which will have to be found by the courts, or by an amendment to these Conditions.

(c) The draftsman must have searched hard and long to discover a word so wide and vague in meaning as “arrangements”. Arrangements by the contractor with his suppliers and sub-contractors, internal staff arrangements, arrangements with his labour—all appear to be included, however private, peculiar or unreasonable they may be and unrevealed to the engineer at the time the tender is accepted or when he gives his instruction or direction. But the engineer will have some help if he obtains as soon as possible, as he should, “a general description of the arrangements and methods of construction which the Contractor intends to adopt”, to which he is entitled under cl. 14,?within 21 days after acceptance of the tender. Presumably the arrangements affected must relate to the works for which the claim is made, not to other contracts which the contractor happens to be carrying out at the same time.

(d) It is the cost which must be beyond that reasonably to have been foreseen, not the instruction or direction. An experienced contractor must be taken to foresee that the engineer will give him the necessary instruction to correct any breach of the contract by the contractor, but even in that case the strict wording of this clause produces the strange result that the contractor may recover if the cost of delay or disruption due to making the correction exceeds the costs which he would have reasonably foreseen. An example of the type of claim with which the engineer may be harassed is a situation where an instruction to make good failure to fence the site to safeguard the public has to be carried out immediately and disrupts the contractor’s arrangements or causes delay with other work. May the contractor claim that owing to the particular time at which he had to carry out the instruction, the costs of delay were “beyond that reasonably to have been foreseen by an experienced contractor at the time of tender”? h″

Note also the different and, it seems, less stringent wording compared with cl. 12—“beyond that reasonably to have been foreseen” instead of “could not reasonably have been foreseen”. If a substantial risk of extra cost is foreseeable it will not be recoverable under cl. 12 (p. 65); under this clause any cost beyond that which is the likely foreseeable cost appears to be recoverable.

This clause is more conducive to chaos than to good order in contract administration and management. At the least, clarification of the meaning and restriction of extra payments to instructions given or confirmed in writing are essential, and should be written into the special conditions under cl. 72. It is hoped that official amendments will be made soon.

?著作權(quán)歸作者所有,轉(zhuǎn)載或內(nèi)容合作請聯(lián)系作者
  • 序言:七十年代末,一起剝皮案震驚了整個濱河市,隨后出現(xiàn)的幾起案子,更是在濱河造成了極大的恐慌赦肃,老刑警劉巖伐割,帶你破解...
    沈念sama閱讀 211,639評論 6 492
  • 序言:濱河連續(xù)發(fā)生了三起死亡事件构灸,死亡現(xiàn)場離奇詭異戴而,居然都是意外死亡收叶,警方通過查閱死者的電腦和手機(jī)勒葱,發(fā)現(xiàn)死者居然都...
    沈念sama閱讀 90,277評論 3 385
  • 文/潘曉璐 我一進(jìn)店門写穴,熙熙樓的掌柜王于貴愁眉苦臉地迎上來顷级,“玉大人,你說我怎么就攤上這事确垫」保” “怎么了?”我有些...
    開封第一講書人閱讀 157,221評論 0 348
  • 文/不壞的土叔 我叫張陵删掀,是天一觀的道長翔冀。 經(jīng)常有香客問我,道長披泪,這世上最難降的妖魔是什么纤子? 我笑而不...
    開封第一講書人閱讀 56,474評論 1 283
  • 正文 為了忘掉前任,我火速辦了婚禮款票,結(jié)果婚禮上控硼,老公的妹妹穿的比我還像新娘。我一直安慰自己艾少,他們只是感情好卡乾,可當(dāng)我...
    茶點故事閱讀 65,570評論 6 386
  • 文/花漫 我一把揭開白布缚够。 她就那樣靜靜地躺著,像睡著了一般误堡。 火紅的嫁衣襯著肌膚如雪雏吭。 梳的紋絲不亂的頭發(fā)上,一...
    開封第一講書人閱讀 49,816評論 1 290
  • 那天悉抵,我揣著相機(jī)與錄音基跑,去河邊找鬼描焰。 笑死,一個胖子當(dāng)著我的面吹牛篱竭,可吹牛的內(nèi)容都是我干的步绸。 我是一名探鬼主播,決...
    沈念sama閱讀 38,957評論 3 408
  • 文/蒼蘭香墨 我猛地睜開眼吕喘,長吁一口氣:“原來是場噩夢啊……” “哼氯质!你這毒婦竟也來了祠斧?” 一聲冷哼從身側(cè)響起,我...
    開封第一講書人閱讀 37,718評論 0 266
  • 序言:老撾萬榮一對情侶失蹤辕漂,失蹤者是張志新(化名)和其女友劉穎吴超,沒想到半個月后,有當(dāng)?shù)厝嗽跇淞掷锇l(fā)現(xiàn)了一具尸體隧期,經(jīng)...
    沈念sama閱讀 44,176評論 1 303
  • 正文 獨居荒郊野嶺守林人離奇死亡仆潮,尸身上長有42處帶血的膿包…… 初始之章·張勛 以下內(nèi)容為張勛視角 年9月15日...
    茶點故事閱讀 36,511評論 2 327
  • 正文 我和宋清朗相戀三年性置,在試婚紗的時候發(fā)現(xiàn)自己被綠了揍堰。 大學(xué)時的朋友給我發(fā)了我未婚夫和他白月光在一起吃飯的照片。...
    茶點故事閱讀 38,646評論 1 340
  • 序言:一個原本活蹦亂跳的男人離奇死亡隐砸,死狀恐怖蝙眶,靈堂內(nèi)的尸體忽然破棺而出褪那,到底是詐尸還是另有隱情博敬,我是刑警寧澤峰尝,帶...
    沈念sama閱讀 34,322評論 4 330
  • 正文 年R本政府宣布,位于F島的核電站祭往,受9級特大地震影響火窒,放射性物質(zhì)發(fā)生泄漏。R本人自食惡果不足惜括勺,卻給世界環(huán)境...
    茶點故事閱讀 39,934評論 3 313
  • 文/蒙蒙 一疾捍、第九天 我趴在偏房一處隱蔽的房頂上張望。 院中可真熱鬧乱豆,春花似錦吊趾、人聲如沸。這莊子的主人今日做“春日...
    開封第一講書人閱讀 30,755評論 0 21
  • 文/蒼蘭香墨 我抬頭看了看天上的太陽。三九已至勇边,卻和暖如春折联,著一層夾襖步出監(jiān)牢的瞬間,已是汗流浹背奕坟。 一陣腳步聲響...
    開封第一講書人閱讀 31,987評論 1 266
  • 我被黑心中介騙來泰國打工, 沒想到剛下飛機(jī)就差點兒被人妖公主榨干…… 1. 我叫王不留执赡,地道東北人函筋。 一個月前我還...
    沈念sama閱讀 46,358評論 2 360
  • 正文 我出身青樓跌帐,卻偏偏與公主長得像,于是被迫代替她去往敵國和親谨敛。 傳聞我的和親對象是個殘疾皇子,可洞房花燭夜當(dāng)晚...
    茶點故事閱讀 43,514評論 2 348

推薦閱讀更多精彩內(nèi)容