2022-04-21(218)Engineering law and the ICE Contracts

1. COPIES OF SOME CONTRACT DOCUMENTS TO BE FURNISHED FREE OF CHARGE “UPON ACCEPTANCE OF THE TENDER”. A useful addition to ensure that the contractor has these documents at an early stage. These words hardly bind the engineer to supply the documents on the very day on which the tender is accepted, but in the case of substantial delay, the contractor could have a claim for any adverse effects on his planning (p. 364).

2. DRAWINGS. Definition cl. 1 (1) (g), p. 25.

3. COPIES NOT FURNISHED FREE OF CHARGE. The contractor is not entitled to free copies of the pricing of the bill, the tender, the written acceptance by the employer or of any contract agreement. Copies of the first two should be retained when tendering, the contractor will have the original of the acceptance, and the agreement should be executed in duplicate. There is no requirement in cl. 7 (1) that the contractor is supplied with more than the original of “modified or further drawings and instructions”.

4. COPYRIGHT. See p. 402, N. 35. The statement that copyright shall “remain in the Engineer” is not completely accurate; copyright in the contract documents will belong to the employer where the engineer is a fulltime employee of his, such as an engineer of a local authority.

For ownership of documents see p. 402.

5. “THE CONTRACTOR MAY…MAKE…ANY FURTHER COPIES REQUIRED BY HIM”. Clearly, this permission is limited to copies required for the works, since the engineer owns the copyright—see the last note.

6. RETURN OF DOCUMENTS BY THE CONTRACTOR. The contractor is not required to return the bill of quantities.

Only “Drawings” and “Specifications” each with a capital letter have to be “returned” under this sub-clause, i.e. those furnished or approved in writing by the engineer within the definition in cl. 1 (1) (f) and (g), and not other drawings, etc., made by the contractor, e.g. for his own temporary works.

The documents are to be returned “At the completion of the Contract”. That stage appears to be reached only with the issue of the final certificate under cl. 60(3) and not earlier with the maintenance certificate, particularly as the contractor may need the documents for preparing his final account.

7. “THE ENGINEER…SHALL SUPPLY…SUCH MODIFIED OR FURTHER DRAWINGS” ETC. See N. 11.

8. “NECESSARY FOR THE PURPOSE OF THE PROPER AND ADEQUATE CONSTRUCTION COMPLETION AND MAINTENANCE OF THE WORKS”—“REQUIRE FOR THE EXECUTION OF THE WORKS OR OTHERWISE UNDER THE CONTRACT”. No reason for this variety of wording is apparent.

9. “THE CONTRACTOR SHALL GIVE ADEQUATE NOTICE IN WRITING” of drawings, etc., required. See N. 11.

10. CLAIMS FOR “FAILURE OR INABILITY OF THE ENGINEER TO ISSUE AT A TIME REASONABLE IN ALL THE CIRCUMSTANCES DRAWINGS OR INSTRUCTIONS”. In view of the importance of disruption claims by contractors, this phrase is discussed separately in ch. 12 on disruption.

11. “DRAWINGS OR INSTRUCTIONS REQUESTED BY THE CONTRACTOR”. This clause can hardly be said to be graced with a rational scheme. Sub-cl. (1) places the duty on the engineer to issue “modified or further drawings” as he considers necessary; nevertheless, the contractor is required by sub-cl. (2) to give “adequate notice in writing” of any “further drawing or specification” that he may require for the execution of the works. and by sub-cl. (3) is entitled to compensation only for delay in the issue of “drawings or instructions requested” and “considered necessary by the Engineer in accordance with sub-clause (1)”.

In view of the ambiguity of the requirement that drawings and instructions must be “requested” to entitle the contractor to claim for delay (not, as could easily have been said if intended, “requested by notice in accordance with sub-clause (2)”), the initial duty placed on the engineer to supply drawings, etc., and the incidental mystery of the change from “drawings and instructions” in sub-cl. (1) to “drawing or specification” in sub-cl. (2) and back again to “drawings or instructions” in sub-cl. (3), it does not seem that “requested” means requested by the contractor by “adequate notice in writing” as specified in sub-cl. (2). Nor does it seem that the contractor is limited to claiming for a period of delay after a request has been made (“at a time” not “within a time”).

Nevertheless, lateness of or lack of clarity or urgency in a request may be relevant to deciding what was a reasonable time for the engineer to provide the drawings or instructions (p. 365). hh

There remains also the very practical point that the contractor has a remedy under this clause for late drawings or instructions only if they have been “requested” by him at some time before receipt. This clause appears to be intended as a comprehensive provision dealing with the contractor’s remedy for delayed instructions or drawings (unlike the equivalent provision of the J.C.T. Standard Forms of building contract, in which the contractor’s common law rights are specifically preserved), so that there is no room for implication of any other term dealing with compensation for delay with drawings or instructions which have not been requested (p. 42). However, in certain circumstances the contractor’s rights under other clauses may come to his rescue. ii?

The problems of delay and disruption claims are discussed at large in ch. 12, but the relationship of the various clauses in these Conditions can be summarised by saying that in so far as performing the work in instructions or drawings would have caused the delay whenever they were issued, then the contractor may have a remedy under cls. 13 or 51 but not under this clause (N. 15); in so far as the contractor suffers delay before instructions or drawings are issued in waiting for them, his only remedy for the cost of that delay is under this clause; if because of the time at which the instructions are issued the contractor has to delay the works after their issue (e.g. in order to pre-plan) he may have the useful alternative to a claim under this clause of claiming under cl. 13 or cl. 51, for instance if the engineer produces some delaying detail which the contractor did not expect and therefore did not request in advance as required by this clause.

In the interests of progress of the works as well as his contractual position if matters do go wrong, it is advisable for the contractor to have a regular office procedure by which in sending his programme he also notifies the dates by which he requires the full drawings and instructions for specified parts of the works. A programme under cl. 14 merely showing a date on which particular work is to be carried out is hardly by itself a sufficient implied request for the drawings and instructions necessary to execute that work so as to satisfy the requirements of this clause.

The contractor should also have a set procedure for giving further written notice in good time of all information he needs, allowing a reasonable period for the engineer to prepare and issue the information and for the contractor himself to do any necessary pre-planning, and recording in what cases and why delay in furnishing the information will disrupt his work. The importance of such records for both the engineer and the contractor is discussed again under the heading of “Claimsmanship” in ch. 17.

Only the engineer or his delegate specifically given all the engineer’s functions or his functions under this clause appear to have power to receive the necessary request, not the engineer’s representative or his assistants (cl. 2 (1)–(3)).

?著作權(quán)歸作者所有,轉(zhuǎn)載或內(nèi)容合作請聯(lián)系作者
  • 序言:七十年代末恋腕,一起剝皮案震驚了整個濱河市茂契,隨后出現(xiàn)的幾起案子,更是在濱河造成了極大的恐慌窿撬,老刑警劉巖治拿,帶你破解...
    沈念sama閱讀 212,383評論 6 493
  • 序言:濱河連續(xù)發(fā)生了三起死亡事件定罢,死亡現(xiàn)場離奇詭異族购,居然都是意外死亡攒盈,警方通過查閱死者的電腦和手機抵拘,發(fā)現(xiàn)死者居然都...
    沈念sama閱讀 90,522評論 3 385
  • 文/潘曉璐 我一進店門,熙熙樓的掌柜王于貴愁眉苦臉地迎上來型豁,“玉大人僵蛛,你說我怎么就攤上這事尚蝌。” “怎么了充尉?”我有些...
    開封第一講書人閱讀 157,852評論 0 348
  • 文/不壞的土叔 我叫張陵飘言,是天一觀的道長。 經(jīng)常有香客問我驼侠,道長姿鸿,這世上最難降的妖魔是什么? 我笑而不...
    開封第一講書人閱讀 56,621評論 1 284
  • 正文 為了忘掉前任倒源,我火速辦了婚禮苛预,結(jié)果婚禮上,老公的妹妹穿的比我還像新娘笋熬。我一直安慰自己热某,他們只是感情好,可當我...
    茶點故事閱讀 65,741評論 6 386
  • 文/花漫 我一把揭開白布胳螟。 她就那樣靜靜地躺著昔馋,像睡著了一般。 火紅的嫁衣襯著肌膚如雪糖耸。 梳的紋絲不亂的頭發(fā)上绒极,一...
    開封第一講書人閱讀 49,929評論 1 290
  • 那天,我揣著相機與錄音蔬捷,去河邊找鬼垄提。 笑死,一個胖子當著我的面吹牛周拐,可吹牛的內(nèi)容都是我干的铡俐。 我是一名探鬼主播,決...
    沈念sama閱讀 39,076評論 3 410
  • 文/蒼蘭香墨 我猛地睜開眼妥粟,長吁一口氣:“原來是場噩夢啊……” “哼审丘!你這毒婦竟也來了?” 一聲冷哼從身側(cè)響起勾给,我...
    開封第一講書人閱讀 37,803評論 0 268
  • 序言:老撾萬榮一對情侶失蹤滩报,失蹤者是張志新(化名)和其女友劉穎,沒想到半個月后播急,有當?shù)厝嗽跇淞掷锇l(fā)現(xiàn)了一具尸體脓钾,經(jīng)...
    沈念sama閱讀 44,265評論 1 303
  • 正文 獨居荒郊野嶺守林人離奇死亡,尸身上長有42處帶血的膿包…… 初始之章·張勛 以下內(nèi)容為張勛視角 年9月15日...
    茶點故事閱讀 36,582評論 2 327
  • 正文 我和宋清朗相戀三年桩警,在試婚紗的時候發(fā)現(xiàn)自己被綠了可训。 大學時的朋友給我發(fā)了我未婚夫和他白月光在一起吃飯的照片。...
    茶點故事閱讀 38,716評論 1 341
  • 序言:一個原本活蹦亂跳的男人離奇死亡,死狀恐怖握截,靈堂內(nèi)的尸體忽然破棺而出飞崖,到底是詐尸還是另有隱情,我是刑警寧澤谨胞,帶...
    沈念sama閱讀 34,395評論 4 333
  • 正文 年R本政府宣布固歪,位于F島的核電站,受9級特大地震影響胯努,放射性物質(zhì)發(fā)生泄漏昼牛。R本人自食惡果不足惜,卻給世界環(huán)境...
    茶點故事閱讀 40,039評論 3 316
  • 文/蒙蒙 一康聂、第九天 我趴在偏房一處隱蔽的房頂上張望贰健。 院中可真熱鬧,春花似錦恬汁、人聲如沸伶椿。這莊子的主人今日做“春日...
    開封第一講書人閱讀 30,798評論 0 21
  • 文/蒼蘭香墨 我抬頭看了看天上的太陽脊另。三九已至,卻和暖如春约巷,著一層夾襖步出監(jiān)牢的瞬間偎痛,已是汗流浹背。 一陣腳步聲響...
    開封第一講書人閱讀 32,027評論 1 266
  • 我被黑心中介騙來泰國打工独郎, 沒想到剛下飛機就差點兒被人妖公主榨干…… 1. 我叫王不留踩麦,地道東北人。 一個月前我還...
    沈念sama閱讀 46,488評論 2 361
  • 正文 我出身青樓氓癌,卻偏偏與公主長得像谓谦,于是被迫代替她去往敵國和親。 傳聞我的和親對象是個殘疾皇子贪婉,可洞房花燭夜當晚...
    茶點故事閱讀 43,612評論 2 350

推薦閱讀更多精彩內(nèi)容